Thursday 14 January 2016

Cold but a Hot Day for most


Wednesday 13th January 2016

28 volunteers turned up on probably the first frosty morning of the year, the day started off cold but soon turned out to be a pleasant dry day, soon many of the volunteers one way or another were feeling the heat!


 



The main task of the day was the mixing of the concrete and filling of the shuttering by the signal box. This will be used as the foundation for the signal box stairs.
Here we see the temporary platform and mixer ready for action.










Elsewhere John C on the mini digger and Steve B on the dumper were bringing the aggregate to the waiting team.










Our youngest volunteer Peter had the job of spreading the dry mixed concrete into the corners of the shuttering.

Also just seen on the left is Steve B with yet another dumper load of aggregate for the mixer.










Around mid day this was the level in the shuttering, only another foot to go .But we were running out of aggregate so off John C went to the suppliers.
With this last bag we just managed to get to line on the inside of the shuttering.

By Saturday the concrete would have set sufficient for the shuttering to be removed .






A bag to finish the job



Meanwhile we had a delivery of the insulation for the station floor.

Although they looked and were light they were one of the most awkward things to lift and carry and with much ado they are now stored in the signal box locking room.










Elsewhere in the car park Rod and Terry were having the first bonfire of the year.
Burning much of the trees, bushes and scrub they had removed from around the ditch and car park.

They were later joined by Brian and others to continue the ditch and car park clearing.








Not just one bonfire but a second, this one was on the north track bed. Gordon finally lit the pile of rubbish that had been there from well into last year, but with the wind and rain nobody had, had a chance to light it.











What must have been the coldest job of the day, went to Keith and Mike . They stood for hours in container 3 priming the many window frames.







The work on the station building was put on hold today as most of the volunteers tackled the filling of the shuttering .

But Bob J did a great job in cutting bricks in half for the station, he must have done about 30, not an easy job.

And finally Vic looking after the shop while still gardening.







Couldn't resist this shot though the window of the signal box, we have had a visit from S & T !!



7 comments:

  1. Great work. A question why is the shuttering higer than the final level, wouldn't it be easier to level cut to size?

    ReplyDelete
    Replies
    1. Because the platform at that point is not fully unfilled yet- look carefully at the photos, and you will see a dip in the level at that point.

      Delete
    2. We try to leave the sheets intact so we could reuse them at a later date. We had a line drawn inside as a level for the height of the concrete.

      Delete
  2. were the sleepers being burned original GWR/BR ones from Broadway?

    ReplyDelete
    Replies
    1. No, they were brought up a couple of years ago to test some levels around the bracket signal.

      Delete
  3. Am I right in saying the Monday team did some brick laying on the station building this week

    ReplyDelete
    Replies
    1. Some blocks were laid on Monday but I don't think any bricks were.

      Delete