Thursday, 23 February 2017

Expecting a Visit from Doris!


Wednesday 22nd February 2017



A mild windy start gave way to showery windy conditions later in the day.
16 volunteers signed in at Broadway today plus the full compliment of 4 in the painting team at Toddington.

Starting with a report from the Toddington marquee, Mike S tells me that, by the end of play, 13 spear fence panels are primed & ready for transporting back to Broadway. Fairview delivered to them 4 dumpy bags of sand. You might ask why painters would require sand and in such a quantity. Well the heavy bags are on loan to act as anchors for the marquee in anticipation of a visit from Storm Doris on Thursday.

                                                                   (Pic. by Mike S)

                                                  Mike T "slapping" some more on
                                                 Brian & Mike S preparing the panels                            
                                                                  (Pics. by Tony)

We started the day at Broadway with roughly 14 volunteers. Terry had to work on his own laying driveway edging slabs, until Rod returned from a meeting, supported by Pat & David providing the concrete. By the end of the day he had laid a record 17 slabs - 15.3 metres ! What do you think of that Rod ?

                      Pat taking a breather from concrete production & wheelbarrow delivery.
                                               Pat assisting with the tamping of concrete.

Tony, John S & Clive were working on internal walls of the station building. Peter Q & Brian T continued with spacing out more ceiling joists for the restaurant area & then filling in with cut blocks.


As mentioned last week, we were getting a visit from Vic Haines Transport. He duly arrived, nice and early, to assist with clearance of the Northern area of  the Broadway site. Firstly he was asked to move piles of catch pit rings onto platform 2 for storage. 2 heavy bridge parapet capping stones & several lamp posts were then loaded & transported to Winchcombe for storage, with assistance from Gordon. A second trip by Vic Haines Transport was necessary later in the day.

                                                    Gordon & Chris assessing the job.
                                                  A  large capping stone being loaded.
                                              Catch pit rings being moved onto platform 2.
.
Workwise it was a short afternoon with rain making it unsuitable for much more block laying & driveway concreting in of edging slabs.
This report is being prepared Thursday am, & I can tell Doris isn't too far away now !


Paul Carter






7 comments:

  1. Doris,is here!. She's certainly making her presence known,now!.

    ReplyDelete
  2. Hi! Good to see the progress being made on the roof. I notice that the roof trusses being painted haven't been riveted. Will this be done after the first coat of paint is applied? Another question, please... Where will the spear fencing go? Is it along the back of platform 2 to match up with the gate recently installed near the signal box?

    ReplyDelete
    Replies
    1. Hi Peter, as you suggest the plan is to send the trusses back for riveting after the first coat of paint. The spear fencing currently being manufactured is destined for the back of platform 1.

      Delete
  3. Just a small point - it's a 'complement' of people, not a 'compliment'.

    ReplyDelete
  4. So let's just compliment the complement involved ☺

    ReplyDelete
  5. So with all the to-ing and fro-ing lets not forget that this is all done by volunteers! You would not get me out the storm!!! so well done every one for even turning up!
    Regards
    Paul & Marion

    ReplyDelete
  6. I am amazed at the good work and progress made with the station building considering the weather of late. Well done to everyone. Regards, Paul.

    ReplyDelete