The change in working days has thrown the Bloggers into turmoil ! Who is doing what and when, anyway it was my turn on Monday but apologies, I didn't bring my camera, so here is a quick catch up of what occurred on Monday and Friday (without lots of pictures).
Platform 2 was power washed from end to end.
The carpenters continued the construction of wooden litter bins.
A painter was fine painting the lamp posts.
The area between the two new gate posts was filled in and now just requires compacting before slabs can be laid and the area finished off.
Elsewhere the cafe and kitchen were in the final throws of being plastered
which by Friday had been completed. The two rooms were then cleared and soon the carpenters will be able to carry on with the paneling and skirting board. Probably at the same time as the painters paint the ceiling and walls!
The electricians were also on site fitting the station canopy lights, not far away the refurbished signs for the Ladies Room and Gentlemen's toilets also got fitted.
Looking to the north.
Looking to the south.
The lamp also got fitted in the Booking Office, all that is required is the fitting of its cover.
Slowly but surely the little things that will make the station look like a heritage station are beginning to appear!